2.4.4 Project Approval

Project requests to include a DA Form 4283 shall be submitted to the DPW Customer Service Division and will include the required Design Team IDG Checklist discussed below. 

Design Team IDG Checklist.

  • The Design Team IDG Checklist is to be completed by the design team to assure the guidelines and standards have been considered in the design process.  The Design Team IDG Checklist is provided in Appendix A.

  • The Designer of Record or Design Agent shall provide a copy of the completed checklist to the Master Planner, together with a signed certification statement with each design submittal. The checklist along with concept site plans and elevations for each design submittal shall be provided to the Master Planner for review. If the Master Planner or designated representative concurs, the plan and the signed checklist are forwarded to the RPPB for final approval. 

  • The accepted checklist shall become a part of the project record files.

 

 

 
 