B.5.10 Summary of Permits

The following table summarizes permitting requirements:

Air Permit Requirements

Permit Activity

Discriminator

Permit    Required ?

Considerations
(I.e., permit type, cost. Time constraints, other

Demolition

All Structures

Yes

County Permit.  $50/Bldg.  2 working days DECAM preparation time.  Need documented asbestos and CFC clearance.

Land Development/  Construction Activities

<1 acre and < 6 months

No

Control dust with watering and best management practices.

 

³ 1 acre but < 25 and < 6 months

Yes

County permit.  $120.  5 working days DECAM preparation time.

 

³ 25 acres or  ³ 6 months

Yes

State permit.  $120 application fee plus $55/hour processing fees.

Open Burning

All open fires

Yes

County permit.  $20.  10 working days DECAM preparation time.  Major restrictions on permissible types of burning.  Normally for thatch reduction, agricultural purposes or fire training.  Not for demolition.  Forbidden Nov-Mar.

Sand  Blasting

All sand blasting

Yes

County Permit.  $40/project.  $150/year.  5 working days DECAM preparation time.  Wet blasting and control plan required.  Test for lead and asbestos prior to start-up.

Road Striping

All road/parking lot projects

Exempt

Use paint without heavy metals (e.g lead-free) and low VOCs.  Report quantity and type of paint use to the DECAM Air Program.   

Road Repair/  Reconstruction

All previously existing roads

Exempt

Control dust with watering and best management practices.

Borrow Areas

Any borrow areas exceeding 1

Yes

All projects with borrow areas exceeding 1 acre or cause the project as a whole to exceed 1 acre must obtain a Land Development/Construction permit.

Asphalt Operations

NA

Exempt

No permit or reporting requirements

Structural Painting

NA

Exempt

Use paints free of RCRA listed metals.  No VOC permit reporting requirements.  Determine if paint preparation will release particulates containing heavy metals or asbestos prior to project start-up.

Spray Painting

All non-structural painting

Yes

Requires an engineered spray booth.  State permit allow several months.  $ varies. Annual emission fees.  Record keeping requirement of paint/solvents by type and content required.

Stationary Combustion Sources (e.g., boilers)

 - Review all boilers and  generators.

Depends on size

Air pollutant emission notices ($120 each).  Annual emission fee/ton.  The DECAM Air Program needs to update equipment inventory and Title V permit.  State permit fee maybe required.

Incinerators

Review all

Yes

Variability of incinerated material requires individual review.

 

 
 